ANSI EIA X12 Preferences

Use this dialog box to select options for the ANSI EIA X12 Wizard, which lets you export project information to other applications that support Version 3040 or Version 3050 of the ANSI EIA X12 Transaction Set 839 Project Cost Reporting.

Contents

Note: For information on how to use the Selected and Secure checkboxes of these options, see Using the Selected and Secure Checkboxes.
FieldDescription
Export wInsight extended information

Select this option to instruct Cobra to export the extended data set. wInsight uses an extended data set for better analysis.

The following are exported from Cobra as extended data:

  • Control account manager
  • Hourly data
  • Future monthly budget
  • ETC
Export variance narrative data

Select this option to instruct Cobra to include the variance narrative entries on the IPMR Format 5 when exporting ANSI EIA X12 data.

Export CSSR data

Selecting this option instructs Cobra to include the CSSR information when exporting ANSI EIA X12 data.

Suppress exporting the CAM field

Select this option to instruct Cobra not to export the CAM field when exporting extended data. This option is available only if you select the Export wInsight extended information option.

Enforce consecutive forecast periods

Select this option to instruct Cobra that if the project is using weekly earned value, the exports will be summarized into monthly periods.

Use yyyymmdd dates instead of yymmdd

Select this option to instruct Cobra to export the dates in yyyymmdd format.

Filter unused WBS/OBS codes

Select this option to instruct Cobra to exclude WBS or OBS codes that do not contain values from the export process.

Export manpower in:

This option allows you to export man power as either FTE (Full-Time Equivalent) or Hours for IPMR Format 4 reports. Selecting Hours creates the IPMR Format 4 using the result code H-Hours in the calculation of resource.

Use alternate code for WBS

Use this field to select a number from 1 to 9 that represents the code position in the control account code file that will be used as the WBS. Cobra exports this control account code instead of the code selected for the Control Account Key Field 1. Selecting 1 means that the first code listed as an attached code in the control account is used as the alternate WBS. Selecting 0 means that the Control Account Field 1 position is used as the WBS.

Use alternate code for OBS

Use this field to select a number from 1 to 9 that represents the code position in the control account code file that will be used as the OBS. Cobra exports this control account code instead of the code selected for the Control Account Key Field 2. Selecting 1 means that the first code listed as an attached code in the control account is used as the alternate OBS. Selecting 0 means that the Control Account Field 2 position is used as the OBS.

WBS Project Office code

Use this field to select a number from 1 to 9 that represents the code position in the Control Account Field 1(WBS) code file. The code position selected is used to extract the Project Officer data. Selecting 1 means that the code in the first code file position in the Control Account Field 1 code file is used. Selecting 0 means that there is no code in the WBS code file that represents the Project Officer code.

OBS Project Office code

Use this field to select a number from 1 through 9 that represents the code position in the Control Account Field 2 (OBS) code file. The code position selected is used to extract the Project Officer data. Selecting 1 means that the code in the first code file position in the Control Account Field 2 code file is used. Selecting 0 means that there is no code in the OBS code file that represents the Project Officer code.


How to...

Create a New Project

Copy Project Preferences


Learn more about...

Options Page of the ANSI EIA X12 Wizard

ANSI EIA X12 Wizard

Projects

Cobra Explorer


Parent Topic:

Preferences Tab of the Project Properties Dialog Box