Add Milestones or Steps
Create milestones and steps for work packages to measure progress.
To add milestones or steps to a work package:
Display the Project view, click a work package in the Spreadsheet pane and click the Milestones/Steps tab.
To add a milestone, take one of the following actions:
- In the Milestone/Step group on the Edit tab, click Milestone > Add Milestone.
- Right-click the Milestones/Steps grid and select Add Milestone on the shortcut menu.
To add a step, take one of the following actions:
- In the Milestone/Step group on the Edit tab, click Step.
- Right-click the Milestones/Steps grid and select Step on the shortcut menu.
Cobra adds a row to the Milestones/Steps grid. Use this row to add information required for a milestone or step, such as description, dates, and weight factor. You cannot modify information about a milestone or step if the work package has a status of Completed.
Note: You can add milestones or steps only if the work package uses any of the progress techniques other than Milestones or Steps, and the Allow entering milestones/steps regardless of Progress Technique option on the Preferences Project tab of the Project Properties dialog box is selected. However, Cobra processes will ignore milestones or steps added to a work package that has a progress technique other than Milestones or Steps. The milestones or steps are for informational purposes only.
How to...
Configure the Application Settings
Learn more about...
Notes Tab of the Application Preferences Dialog Box
Spreadsheet Pane of the Project View
General Tab of the Project View
Milestones/Steps Tab of the Project View