Cobra Help

Assign Sub-Projects to a Master Project

Use the Sub-Projects tab of the Project Properties dialog box to assign sub-projects to a master project.

To assign sub-projects to a master project:

  1. Display Project Properties dialog box and click the Sub-Projects tab.

  2. Click Add.

  3. In the Project Lookup dialog box, select the projects that you want to add as sub-projects to the master project.

  4. Click Select to add the selected projects to the master project.


How to...

Display the Project Properties Dialog Box from an Open Project

Display the Project Properties Dialog Box Tabs from an Open Project File

Display the Project Properties Dialog Box Tabs without Opening a Project File

Display the Project Properties Dialog Box without Opening the Project

Create a New Project

Add a New Control Account

Add a New Work Package


Learn more about...

Sub-Projects Tab of the Project Properties Dialog Box

Cobra Explorer

Projects

Multiproject Guidelines


Parent Topic:

Procedures