Use the General tab of the Project Properties dialog box's Classes tab to assign a budget source to a budget class.

To assign a budget source to a budget class:

  1. Display Project Properties dialog box and click the Classes tab.

  2. In the Classes grid, select a class.

    You can only assign a budget source to a budget class.

  3. Click the General tab.

  4. Click the Obtain budget from field and select the budget source that you want to assign to the class.

  5. Click Apply.