Calculate Forecast Spread by Existing EAC

A set of examples may help demonstrate how Cobra calculates forecast spread according to the Existing EAC method.

Scenario: Extend Dates

Assume that you have the following data:

Current Spread

  • Forecast Start Date: March 31, 2023
  • Forecast Finish Date: May 30, 2023

Periods

Totals

March

April

May

ETC Hours

50

10

30

10

Then, extend the forecast start and finish dates as follows:

  • Forecast Start Date: Feb 28, 2023
  • Forecast Finish Date: June 30, 2023

Periods

Total

February

March

April

May

June

ETC Hours

50

0

10

30

10

0

After the Calculate Forecast spread, the spread would be as follows:

Periods

Total

February

March

April

May

June

ETC Hours

50

6

10

18

10

6

Scenario: Shrink Dates

Assume that you have the following data:

  • Forecast Start Date: Feb 28, 2023
  • Forecast Finish Date: June 30, 2023

Periods

Total

February

March

April

May

June

ETC Hours

50

6

10

18

10

6

Then, shrink the forecast start and finish dates as follows:

  • Forecast Start Date: March 31, 2023
  • Forecast Finish Date: May 30, 2023

Periods

Total

February

March

April

May

June

ETC Hours

50

6

10

18

10

6

After the Calculate Forecast spread, the spread would be as follows:

Periods

Total

March

April

May

ETC Hours

50

2.67

24.57

2.67

Scenario: Shift of Dates with the Same Number of Periods for Planned Work Package

Assume that you have the following data:

  • Forecast Start Date: March 31, 2023
  • Forecast Finish Date: May 31, 2023

Periods

Total

March

April

May

ETC Hours

30

0

10

20

Then, move the forecast start and finish dates as follows:

  • Forecast Start Date: April 30, 2023
  • Forecast Finish Date: June 30, 2023

Periods

Total

March

April

May

June

ETC Hours

30

0

10

20

0

After the Calculate Forecast spread, the spread would be as follows:

Periods

Total

April

May

June

ETC Hours

30

0

10

20


How to...

Create a Forecast

Set Up a Retain EAC Forecast with the Scale EAC Option

Copy Budget to a Manual Forecast Using the Reclass Wizard


Learn more about...

Retain EAC

Forecast Preferences

Calculate Forecast Process


Parent Topic:

How Cobra Spreads ETC