Copy Element of Cost Value to Child Resources
Use this procedure to copy the element of cost value attached to a parent resource to its child resources.
To copy element of cost value to child resources:
Display the Resource view for the resource file you want to update.
In the Resource view, click a parent resource and take one of the following actions:
- In the Codes group on the Edit tab, click Copy Element of Cost.
- Right-click the Resources grid and select Copy Element of Cost.
Note: The Copy Element of Cost option is enabled only for resources with child resources.Click Yes when the confirmation message displays.
Click
to save your changes.
Learn more about ...
How to...
Display the Resource View using the Cobra Button
Display the Resource View using the Resources Group Bar
Assign Element of Cost to a Resource