Define Resource Apportionment

Use the Apportionment Definition tab of the Resource view to define resource apportionment.

To define resource apportionment:

  1. Display the Resource view.

  2. In the Resource view, select a resource or child resource from the grid.

    This is the resource that Cobra will apportion.

  3. Click the Apportionment Definition tab.

  4. On the Apportionment Definition tab pane, select the Resource budgeted by apportionment option.

    Note: If you do not select this option, the fields and options on the Apportionment Definition tab will remain unavailable.
  5. In the Source Result field, select the result you want to associate with the apportioned resource and click Add.

  6. In the Resource Lookup dialog box, select the resource you want to use as the source for the apportioned resource.

    You can select multiple resources or child resources.

  7. Click Select to add the selected base resource to the Source Resources field.

  8. Click on the Quick Access toolbar to save the apportioned resource.

    Note: The order number indicates the order by which the selected resource is calculated with respect to other resources. Each apportioned resource can be calculated from one or multiple resources within the same resource file.

How to...

Perform Apportionment Calculations

Perform Apportionment Mapping

Display the Resource View using the Cobra Button

Display the Resource View using the Resources Group Bar


Learn more about...

Apportionment

Apportionment Setup Steps

Apportionment Calculations

Apportionment Process

Apportionment Mapping

Apportionment Mapping Tags


Parent Topic:

Apportionment Definition Tab of the Resource View