Cobra Help

Display the Total Row in the Project View

Follow this procedure to display the Total row in the Project view.

To display the Total row:

  1. Display the Project view.

  2. On the Edit tab in the Data group, perform one or both of the following actions:

    • Select the Show Project Totals option to display Total row values in the Spreadsheet pane.
    • Select both the Show Project Totals option and the Show Summary Time-phase option to display the Total row values in the Time-phase pane.

How to..

Display the Project View


Learn more about...

Spreadsheet Pane of the Project View

Time-phase Pane of the Project View


Parent Topic:

Procedures