Log Transaction Page of the Project Audit Wizard
Use this page to update the project log directly with four types of transactions: Negotiated Changes, New Unpriced Work, Allocated Management Reserve, and New Over Target Baseline.
You can enter the amount of funds to be transferred between accounts for each transaction.
Transaction Group Box
Use this group box to select the transaction type and specify the related fields to update your project's log.
| Field | Description |
|---|---|
| Transaction Type | Use this field to select your transaction type. Your options are:
|
| Amount | Use this field to enter the amount of the transaction.
Note: This field displays OTB Amount if you select New Over Target Baseline Dates in the Transaction Type field. |
| CLIN | Click this field to display the Lookup dialog box and select a CLIN code field from the list of codes in the assigned CLIN code file.
Note: This field does not display if the selected project is a master project. This field is disabled if the CLIN Code field for the selected project is not configured. For more information, see Fields Tab of the Project Properties Dialog Box. |
Additional Fields
This section describes the additional fields that display for each transaction type.
Transaction Type | Description |
|---|---|
New Unpriced Work | The following field displays if you select New Unpriced Work in the Transaction Type field:
|
Negotiated Changes | The following fields display if you select Negotiated Changes in the Transaction Type field:
|
New Over Target Baseline | The following fields display if you select New Over Target Baseline in the Transaction Type field:
|
Account Fields Group Box
This group box displays the fields that are updated as you populate the Amount field, as well as the additional fields for each transaction type.
- Negotiated Cost
- Authorized Unpriced Work
- Management Reserve
- Contract Budget Base
- Distributed Budget
- Contract Ceiling
- Undistributed Budget
Over Target Baseline
- Total OTB
- Distributed OTB
- Undistributed OTB
- OTB Management Reserve
While updating and computing the OTB-related fields, certain transaction fields are impacted, while others remain unaffected.
- Negotiated Cost: This field is not impacted by an OTB transaction.
- Contract Budget Base: This field is not impacted by an OTB transaction.
- Distributed Budget: This field is directly impacted by the Distributed OTB amount. For example, if OTB resources are allocated to a work package that totals $100,000, Distributed Budget will increase by $100,000.
- Undistributed Budget: This field is directly impacted by the Undistributed OTB amount. For example, if an OTB transaction is made where OTB Allocated to UB totals $50,000, Undistributed Budget will increase by $50,000.
- Management Reserve: This field is directly impacted by the OTB Management Reserve amount. For example, if an OTB transaction is made where OTB Allocated to MR totals $30,000, Management Reserve will increase by $30,000.
- Fee Amount: This field is not impacted by an OTB transaction.
Video
| Title | Description |
|---|---|
| Using OTB in the IPMR Reports and IPMDAR Export | Learn how to implement an over target baseline for display in the IPMR Reports and the IPMDAR Export. |
How to...
Learn more about...
Capturing OTB Transactions in Audit Reports
Using OTB in the IPMR CPR Reports and IPMDAR Exports
Round off Audit Log Transaction