Move a Work Package

Use the Move Work Package dialog box to create a new work package by moving an existing one from one control account to another control account or to within the same control account using a different work package name.

This feature is similar to copying a work package, except that when you move a work package, Cobra deletes that work package from its original location.

To move a work package:

  1. Display the Project view, click a work package and take one of the following actions:

    • In the Tasks group on the Edit tab, click Move.
    • Right-click the Spreadsheet pane and select Move on the shortcut menu.
  2. Use the fields and options in the Move Work Package dialog box to create a new work package.

  3. Click OK.


How to...

Display the Project View

Add a New Control Account

Add a New Work Package

Rename a Control Account

Rename a Work Package

Move a Control Account

Copy a Control Account

Copy a Work Package


Learn more about...

Spreadsheet Pane of the Project View

General Tab of the Project View

Move Work Package Dialog Box


Parent Topic:

Procedures