Procedures
Follow the procedures in this section to utilize the Calculate Forecast process.
Related Topics:
Use this procedure to create a project forecast.
Set Up a Retain EAC Forecast with the Scale EAC Option
Use this procedure to set up the retain EAC forecast with the scale EAC options.
Copy Budget to a Manual Forecast Using the Reclass Wizard
If you select a manual forecast, use the Reclass Wizard to copy the budget to the new forecast at the beginning of a project or when new scope is added.
Export Time-Phased Resource Assignments to Excel
Use the Assignment Export utility to update a forecast by exporting time-phased resource assignments to Excel.
Import Time-Phased Resource Assignments from Excel
Use the Assignment Import utility to update a forecast by importing time-phased resource assignments from Excel.
Use the Calculate Forecast Wizard to estimate the final cost of the project at any given time during its course.