Reconcile Budgets and Forecasts

Use the reconciliation process when the spread of the budget no longer matches the resource total (budget at completion or BAC) or when the spread of the forecast no longer matches the ETC(estimate to complete).

To perform a reconciliation:

  1. Display the Project view and select the resource that belongs to a budget or forecast class.

  2. In the Assignments group on the Edit tab, click Spread > Reconcile.