Use the Sub-Projects tab of the Project Properties dialog box to remove sub-projects from a master project.

To remove sub-projects from a master project:

  1. Display the Project Properties dialog box and click the Sub-Projects tab.

  2. Select a project.

  3. Click Remove and then click Apply.