Run the Rolling Wave Process

The rolling wave process splits monthly data into weekly data for future periods and consolidates data in past periods.

You need to advance the calendar and roll the wave at the end of each month. While it is only necessary to roll the wave at month end, it is a good practice to run it each time you advance the calendar.

Rolling wave processing can also be done through the API.

To run the rolling wave process:

  1. Display the Rolling Wave Wizard by taking one of the following actions:

    • In the Status group on the Processes tab, click Rolling Wave.
    • In the Cobra Explorer, click the Projects group bar, right-click the Projects pane, and select Rolling Wave on the shortcut menu.
  2. Use the pages of the Rolling Wave Wizard to collapse past periods or expand future periods of the calendar for a selected project.


How to...

Run the Rolling Wave Process Without Advancing the Calendar


Learn more about...

Rolling Wave

Rolling Wave Dialog Box of the Project Properties Dialog Box

Rolling Wave Process

Rolling Wave Process or Weekly Earned Value


Parent Topic:

Procedures