Cobra Help

Slip a Project

Use the Slip Wizard to move an entire project or selected control accounts within a project to new dates. This procedure is helpful when you are pricing a contract before you create a schedule.

To slip a project:

  1. Display the Slip Wizard by completing one of the following actions:

    • In the Process group on the Processes tab, click Slip.
    • In the Cobra Explorer, click the Projects group bar, right-click the Projects pane, and select Slip on the shortcut menu.
  2. Use the Slip Wizard pages to slip a project or control account.

How to...

Enter Project Dates

Calculate Forecast


Learn more about...

Slip

Forecasts

Calendars

General Tab of the Application Preferences Dialog Box

Spreadsheet Pane of the Project View


Parent Topic:

Procedures