Cobra Help

Zero-Out Data Wizard

To set the time-phased resource values of a selected budget, forecast, progress, or actual class to zero, you must complete the information required on each page of the Zero-Out Data Wizard.


Project Selection Page of the Zero-Out Data Wizard

Use this page to select the project that you want to set the budget, forecast, progress, or actual time-phased resource values to zero.

Options Page of the Zero-Out Data Wizard

Use this page to select the option you want to use when running the Zero-Out Data process.

Criteria Selection Page of the Zero-Out Data Wizard

Use this page to select the criteria for running the Zero-Out Data process.

Classes Page of the Zero-Out Data Wizard

Use this page to select a class for which you want to run the Zero-Out Data process.

Date Range Page of the Zero-Out Data Wizard

Use this page to select the period or date range for which you want to run the Zero-Out Data process.

Confirmation Page of the Zero-Out Data Wizard

This page informs you that Cobra has all the information it needs to run the Zero-Out Data process.

Process Running Page of the Zero-Out Data Wizard

This page displays the progress status while Cobra zeroes out the values of the selected class.

Process Complete Page of the Zero-Out Data Wizard

This page informs you that Cobra has completed zeroing out the values of the selected class.


Parent Topic:

Zero-Out Data