|  Field  |  Description  | 
 
		   
			 | Search 
			  | 
 
			 By default, the dialog box displays all resources, but you can use either or both of the two 
				Search fields to restrict the list: 
				
 
				 When you select a search in the top 
				  Search field, 
				  employees are listed first, followed by generic resources, if the search results include both types of resources. However, if you use the bottom 
				  Search field, the results are sorted alphabetically by name, so 
				  employees and generic resources are likely to be intermingled. 
				 
 
			  | 
 
		  
 
		   
			 | Resource 
			  | 
 
			  
				 This grid column displays a list of the resources based on your entries in the two 
				  Search fields. 
				 
 
				Select the check boxes next to the resources that you want to assign to the 
				  project. The number selected displays below the grid. 
				 
 
				Click the name to display a tooltip containing additional 
				  employee or generic resource information. For an 
				  employee, you can view job title, 
				  organization, labor category, utilization target percentage, hours per day, status, and email address. For generic resources, you can view 
				  organization, labor category, and status. 
				 
 
			  | 
 
		  
 
		   
			 | Scheduled % 
			  | 
 
			  
				 For each 
				  employee, this grid column displays the percentage of available hours in the plan date range that are currently scheduled for the selected 
				  project or for any other 
				  project. The plan date range used in this calculation is the date range for the highest-level WBS element displayed in the WBS grid. 
				 
 
				Scheduled % = (Employee's total scheduled hours in plan date range / (Employee's hours per day x Total work days in plan date range)) x 100 
				 
 
				This column is blank for generic resources. 
				 
 
			  | 
 
		  
 
		   
			 | Clear Selections 
			  | 
 
			  
				 If you select some resources and then decide you want to clear all of those selections and start over, click 
				  Clear Selections. 
				 
 
				If no resources are selected, this option does not display. 
				 
 
			  | 
 
		  
 
		   
			 | Hard Book 
			  | 
 
			  
				 If you consider the new assignments hard booked, select this check box. 
				 
 
				This check box is only available if 
				  DPS is configured to use soft and hard booking and if you have the required security access to hard book assignments. 
				 
 
			  | 
 
		  
 
		   
			 | Select and Level 
			  | 
 
			  
				 This grid displays the WBS hierarchy in 
				  Level, along with any existing resource assignments. If you opened the Assign Resources to 
				  Project dialog box from the top-level 
				  project row in the 
				  Project View grid, the entire WBS hierarchy for that 
				  project is available in this grid. If you opened the dialog box from a lower-level WBS element, only that element and the part of the hierarchy under that element are available. Expand the hierarchy to display the WBS elements to which you want to assign the selected resources, and click 
				  + in 
				  Select next to each of those elements. 
				 
 
				These new assignments are only pending assignments at this point. The actual assignments and update of the plan occur when you click the 
				  Assign button at the bottom of the dialog box. The number of pending assignments displays next to the 
				  Assign button. 
				 
 
				You can only assign resources to the lowest-level WBS elements in each branch of the WBS. A 
				  + displays only next to those elements. You can also expand lowest-level elements to display any resources that are already assigned to them. 
				 
 
			  | 
 
		  
 
		   
			   
			  | 
 
			  
				 If you add an assignment and then want to remove that assignment, hover over the resource row in the WBS grid and click 
				    at the end of the row. 
				 
 
				This option is only available for pending resource assignments. To delete an assignment that was added to the plan previously, use the deletion option in either the 
				  Project View grid or the Resource View grid. 
				 
 
			  | 
 
		  
 
		   
			 | Assign 
			  | 
 
			 Click this button to confirm the assignments, close the dialog box, and update the plan information in the 
				Project View grid. 
			  |