You can display any of the following columns in the middle section of the grid in Billing view. Click 
		   next to the upper-right corner of the grid to select the columns you want.
 next to the upper-right corner of the grid to select the columns you want. 
		
 
		Note that as you make entries in calendar period columns, columns in this middle section of the grid that contain calculated values based on the calendar period entries, such as planned billing amounts, are not updated immediately. Instead, 
		  DPS displays those values with a strikethrough to indicate that they are no longer current. When you move to another grid row or otherwise move off of the current row, all grid cells with out-of-date values are automatically recalculated, and the strikethrough removed. 
		
 
		| Field | Description | 
|---|
 
		   
			 | Assignment Start | For a WBS row, this column displays the start date for the earliest resource assignment for the WBS element. 
				 For a resource row, this column displays the start date for that resource's assignment for the WBS element. You can enter or select the date. 
				 If you change this date and the resource row has no planned hours, a message displays asking if you want to move the assignment end date also to preserve the same number of days between the two dates. 
				 If you change this date and the resource row has planned hours, the Reschedule Labor Assignments dialog box displays so you can specify how you want the hours distributed when the assignment is rescheduled. 
				 If you change this date in a way that places any part of the assignment date range outside of the plan date range for the parent WBS row, a message displays asking if you also want to change the plan date range. Click 
				  Change Dates to have 
				  DPS adjust the plan dates to include the complete assignment date range. It is possible that plan dates at higher levels of the WBS may also be changed so that they include all plan dates below them in the WBS. 
				 | 
 
		   
			 | Assignment End | For a WBS row, this column displays the end date for the latest resource assignment for the WBS element. 
				 For a resource row, this column displays the end date for that resource's assignment for the WBS element. You can enter or select the date. 
				 If you change this date and the resource row has planned hours, the Reschedule Labor Assignments dialog box displays so you can specify how you want the hours distributed when the assignment is rescheduled. 
				 If you change this date in a way that places any part of the assignment date range outside of the plan date range for the parent WBS row, a message displays asking if you also want to change the plan date range for that row. Click 
				  Change Dates to have 
				  DPS adjust the plan dates to include the complete assignment date range. It is possible that plan dates at higher levels of the WBS may also be changed so that they include all plan dates below them in the WBS. 
				 | 
 
		   
			 | Baseline Billing | This column displays the sum of the planned labor amounts, at billing, that is saved in the baseline for the selected WBS row. The baseline acts as a snapshot of the plan at a certain point in time. To save a baseline, click 
				Actions and click 
				Save Baseline on the Actions menu. You can have only one baseline version for any plan. Any changes you make to the existing baseline will overwrite the previous baseline data. After a baseline exists, you can only change the baseline if your role has appropriate access rights. 
				 | 
 
		   
			 | Baseline Hours | This column displays the sum of the planned labor hours that is saved in the baseline for the selected WBS row. The baseline acts as a snapshot of the plan at a certain point in time. To save a baseline, click 
				Actions and click 
				Save Baseline on the Actions menu. You can have only one baseline version for any plan. Any changes you make to the existing baseline will overwrite the previous baseline data. After a baseline exists, you can only change the baseline if your role has appropriate access rights. See the Planning Toolbar online help topic for more information. 
				 | 
 
		   
			 | Calculated % Complete | This column displays the percent complete for the WBS elements and resources, as of the 
				JTD date: (JTD hours / 
				EAC hours) x 100. | 
 
		   
			 | Contract | This column displays the labor contract amount, at billing, for the WBS element. | 
 
		   
			 | Contract Less 
				EAC Billing | This column displays the variance between the labor contract amount and the 
				  estimate-at-completion (EAC) labor amount for the WBS element, at billing, as of the 
				  JTD date. Negative amounts display in red. 
				  Calculation: Labor contract amount - 
				  EAC labor amount 
				 | 
 
		   
			 | Contract Less 
				JTD Billing | This column displays the variance between the labor contract amount and the 
				  JTD labor amount, at billing, for the WBS element as of the 
				  JTD date. Negative amounts display in red. 
				  Calculation: Labor contract amount - 
				  JTD labor amount 
				 | 
 
		   
			 | EAC Billing | This column displays the sum of the 
				JTD labor amount and the 
				estimate-to-complete (ETC) labor amount for the WBS element at billing. Calculation: 
				  JTD labor amount as of 
				  JTD date + 
				  ETC labor amount from day after 
				  JTD date forward 
				 | 
 
		   
			 | ETC Billing | This column displays the 
				ETC labor amount, at billing, for the WBS element. This is the planned labor amount required from the day after the 
				JTD date through the end of the plan to complete the 
				project, 
				phase, or 
				task. Calculation: Planned labor amount at billing from day after 
				  JTD date forward 
				 | 
 
		   
			 | EAC Hours | This column displays the 
				EAC hours for the WBS elements and resources: 
				JTD hours as of the 
				JTD date + 
				ETC hours from day after 
				JTD date forward. | 
 
		   
			 | ETC Hours | For a WBS row, this column displays the sum of all 
				  ETC hours for the resources assigned to that WBS element. The 
				  ETC hours are planned hours for dates in each assignment range that are later than the 
				  JTD date. 
				 For a resource row, this column displays that resource's total 
				  ETC hours for the WBS element. 
				  You can enter hours in this field for any WBS element at any level of the structure if that element has resources assigned. When you do, 
				  DPS allocates the hours to resources and to future calendar periods for that assignment row. If you enter total 
				  ETC hours for a parent WBS element and then expand the WBS structure in the grid to display assignment rows at lower levels, 
				  DPS further allocates the hours to each calendar period for each lower-level row, including the resource rows. Likewise, if you change the scale of the calendar period columns (from Weeks to Months, for example), 
				  DPS reallocates the hours for the new scale. 
				 If you enter hours in this field for a resource, 
				  DPS allocates the hours to the future calendar periods for that resource assignment. 
				 How the hours are allocated to resources and to calendar period grid columns depends on whether or not 
				  ETC  hours have already been entered in calendar period columns for the affected assignments: 
				  
				  If none of the affected resource assignments currently has any 
					 ETC hours, the hours are allocated to each resource and calendar period in proportion to the number of work days remaining for them. (Effectively, the hours are spread equally among all work days for all resources.) 
				  If one or more of the affected resource assignments currently has 
					 ETC hours, the hours you enter are allocated to each resource and calendar period in proportion to its current number of 
					 ETC hours. Resources and calendar periods that currently have no 
					 ETC hours receive no allocation. 
				  If the assignment date range for the row includes no more work days that are later than the 
				  JTD date, you cannot enter hours in this field. 
				 | 
 
		   
			 | JTD Billing | This column displays the 
				JTD labor amount, at billing, for the WBS element, as of the 
				JTD date. Calculation: Sum of actual posted and unposted labor charges 
				 | 
 
		   
			 | JTD Hours <JTD date> | For a WBS row, this column displays the sum of the posted and unposted 
				  JTD actual hours charged to the WBS element by assigned resources, as of the 
				  JTD date. The 
				  JTD date displays as part of the column heading. 
				 For a resource row, this column displays the 
				  JTD actual hours that resource charged to the WBS element, through the 
				  JTD date. 
				 If you use the API or the Historical Labor import to bring in hours charged to 
				  projects, 
				  JTD hours are automatically updated, just as they are if you enter the time in 
				  DPS. Updating 
				  JTD hours, in turn, also affects 
				  ETC and 
				  EAC calculations. If you enter time for a 
				  project, or if the import process or API imports a labor transaction for a 
				  project, and no assignment exists for the 
				  employee for the WBS element to which the labor is charged, a new assignment is created with 
				  JTD hours but no planned hours. 
				   
				 | 
 
		   
			 | Notes | Click  in this column to enter notes related to the WBS element. Be aware that a note is attached to the WBS element, not to the plan. If you save the baseline, the current version of the note is not saved as part of the baseline. If you publish the plan, the current version of the note is not part of the published plan. If you revert plan changes, changes you made to a note are not reverted. 
				   
				 The plan notes are also displayed in an info bubble, along with other information for a WBS element, when you click on the WBS element in any of the planning grids in the 
				  Projects hub or in Resource Management. 
				 This option is not available for resource rows. 
				 | 
 
		   
			 | Plan Start | For a WBS row, this column displays the plan start date for the WBS element. You can enter or select the date. When you enter this plan date, the corresponding plan date on the Expenses and 
				  Consultants tabs is updated also. 
				 If you change this date and the WBS row has no planned hours, a message displays asking if you want to move the plan end date also to preserve the same number of days between the two dates. 
				 If you change this date and the WBS row has planned hours, the Reschedule Plan Dates dialog box displays so you can specify how you want the hours distributed when the plan is rescheduled. 
				 If you select a date that is earlier than the plan start date for any higher-level WBS elements in the same branch, those plan start dates are adjusted accordingly. If you select a date that is later than either the plan start dates for any lower-level WBS elements or any assignment start dates in the same branch, those start dates are adjusted accordingly. 
				 | 
 
		   
			 | Plan End | For a WBS row, this column displays the plan end date for the WBS element. You can enter or select the date. When you enter this plan date, the corresponding plan date on the Expenses and 
				  Consultants tabs is updated also. 
				 If you change this date and the WBS row has planned hours, the Reschedule Plan Dates dialog box displays so you can specify how you want the hours distributed when the plan is rescheduled. 
				 If you select a date that is later than the plan end date for any higher-level WBS elements in the same branch, those plan end dates are adjusted accordingly. If you select a date that is earlier than either the plan end dates for any lower-level WBS elements or any assignment end dates in the same branch, those end dates are adjusted accordingly. 
				 | 
 
		   
			 | Planned Billing | For a WBS row, this column displays the sum of all amounts, at billing, for planned hours (past and 
				  ETC hours) for the resources assigned to that WBS element. 
				 For a resource row, this column displays the sum of all amounts, at billing, for planned hours (past and 
				  ETC hours) for that resource's assignment for the WBS element. 
				 | 
 
		   
			 | Planned Hours | For a WBS row, this column displays the sum of all planned hours (past and 
				  ETC hours) for the resources assigned to that WBS element. 
				 For a resource row, this column displays the sum of all planned hours (past and 
				  ETC hours) for that resource's assignment for the WBS element. 
				 | 
 
		   
			 | Planned Less 
				EAC Billing | For a WBS row, this column displays the difference between the total planned labor amount, at billing, for that WBS element and the 
				  EAC amount, at billing, for the WBS element as of the 
				  JTD date. 
				 For a resource row, this column displays the difference between the planned labor amount, at billing, for that resource's assignment for the WBS element and the 
				  EAC amount, at billing, for that resource's assignment for the WBS element as of the 
				  JTD date. 
				 | 
 
		   
			 | Planned Less 
				EAC Hours | For a WBS row, this column displays the difference between the total planned hours for that WBS element and the 
				  EAC hours for the WBS element as of the 
				  JTD date. 
				 For a resource row, this column displays the difference between the planned hours for that resource's assignment for the WBS element and the 
				  EAC hours for that resource's assignment for the WBS element as of the 
				  JTD date. 
				 | 
 
		   
			 | Planned Less 
				JTD Billing | For a WBS row, this column displays the difference between the total planned labor amount, at billing, for that WBS element and the amount, at billing, for the 
				  JTD actual hours charged to the WBS element as of the 
				  JTD date. 
				 For a resource row, this column displays the difference between the planned labor amount, at billing, for that resource's assignment for the WBS element and the amount, at billing, of the 
				  JTD actual hours charged to the WBS element for the resource as of the 
				  JTD date. 
				 | 
 
		   
			 | Planned Less 
				JTD Hours | For a WBS row, this column displays the difference between total planned hours for that WBS element less the 
				  JTD actual hours charged to the WBS element as of the 
				  JTD date. 
				 For a resource row, this column displays the difference between the planned hours for that resource's assignment for the WBS element less the 
				  JTD actual hours charged to the WBS element for the resource as of the 
				  JTD date. 
				 |