Convert Project Keys
Use the Project Key Conversion utility to change a project number or to combine (close out) project data into a single project.
Before you combine projects, it is important to consider if the projects have associated plans.
When you combine
project numbers,
DPS:
- Combines budgets and data in the project financials tables.
- Deletes billing terms and invoice detail (you cannot reprint old invoices).
- Updates the accounts receivable paid period to the most recent period.
- Combines plan data for the projects.
In addition to combining data between two existing project numbers, you can use the Project Closeout Utility to set up a new project number in which to close out project numbers that are no longer in use. See the Project Closeout Utility for additional information.
Prerequisite: Back up your DPS database.
To change or combine project numbers:
- On the Navigation menu, click .
- Complete the fields on the Key Convert Projects form.
- If you are combining existing projects, select the Combine existing Projects check box.
-
Select one of the following actions:
Option Description To save the conversion to run later Click Save. To run the conversion now Click Run. To schedule the conversion to run on a regular basis via the process server Click Schedule and complete the information on the Schedule dialog box.