Percent Completes for Individual Labor Codes and Expense Accounts
You can enter percent completes at the individual labor code and expense account level. Use this method when labor codes or expense accounts have different percentages of completion.
Enter individual percent completes in the % Complete field on the following Project Budget Worksheet tabs, as needed: Labor Costs, Expense Costs, Labor Billing, Expense Billing.
Example
For example, if you enter individual labor and expense percent completes for each of your labor codes and account numbers, DPS calculates the project's overall percent complete as follows.
This example assumes that you have entered overall, labor, and expense percent complete information on the Project Budget Worksheet.
Labor Budget
Labor Code | Labor Budget | Percent Complete | Earned Labor | Budgeted Overhead Percentage | Earned Overhead | ||
---|---|---|---|---|---|---|---|
A0000 | $2,500 | x | 20% = | $500 | x | 210% | $1,050 |
A1000 | $4,000 | x | 30% = | $1,200 | x | 210% | $2,520 |
$6,500 | $1,700 | $3,570 |
Expense Budget
Account Number | Expense Budget | Percent Complete | Earned Expenses | |
---|---|---|---|---|
511.00 | $1,000 | x | 45% = | $ 450 |
512.00 | $2,000 | x | 40% = | $ 800 |
$3,000 | $1,250 |
Calculations
Calculation | Amount |
---|---|
Total Earned Labor + Total Earned Overhead + Total Earned Expenses Total Project Earned |
$1,700 $3,570 $1,250 $6,520 |
Total Labor Budget + Total Overhead Budget + Total Expense Budget Total Project Budget |
$ 6,500 $13,650* $ 3,000 $23,150** |
Total Project Earned/Total Project Budget = Overall Percent Complete |
$6,520/$23,150 = 28.16% |
* The Total Overhead Budget is determined by multiplying the Total Labor Budget ($6,500) by the Budgeted Overhead Rate (210%). The Total Overhead Budget in the above example is equal to $13,650.
** The Total Project Budget is the sum of the budgeted amounts in the Labor, Overhead, Direct Consult, Other Direct Exp, Reimb Consult, and Other Reimb fields.
Overhead Percentage Used
DPS uses the overhead percentage specified for the project record in the Projects hub.
If no percentage is entered in the Projects hub, DPS uses the overhead rate specified for the project’s organization.
If DPS does not find a percentage for either of these options, it uses the enterprise-wide rate specified in
.