How Overall Percent Completes are Calculated
In calculating the overall percent complete for a project, DPS uses all the record-level percent complete figures unless you specify overrides.
This figure is a weighted average percent complete, calculated in this way:
(All Percent Completes * Their Budgets) / Total Project Budget
All percent completes also include a percent complete for overhead, which is equal to the weighted average percent complete for labor.
DPS displays the overall percent complete in the Budget Summary dialog box.