Assign Cost Rate Methods and Tables to Projects

Enter a cost rate method and rate table for each project, phase, or task that uses an effective date cost rate table.

You can enter a method and table at the highest WBS (project) level, and then enter a method and table at one or more of the project's lower WBS levels to override the rate at the highest WBS level.

To assign cost rate methods and tables to projects:

  1. On the Navigation menu, click Hubs > Projects.
  2. On the Projects hub form, select the project, phase, or task record.
  3. Click the Accounting tab.
  4. In the Cost Method field in the Cost and Pay Rates section, select the method by which to determine each employee's cost rate for this project, phase, or task.
  5. If you select a table-based method in the Cost Method field, use the Cost Table field to select the rate table to use for this project, phase, or task.
  6. Click Save.