Field | Description |
Project
|
This column displays the selected
project's number.
|
Project Name
|
This column displays the selected
project's name.
|
Phase
|
This column displays the
phase's number.
|
Phase Name
|
This column displays the
phase's name.
|
Task
|
This column displays the
task's number.
|
Task Name
|
This column displays the
task's name.
|
Overall % Complete
|
This column contains the same data as the following fields:
-
Overall Pct Comp on the Accounting tab of the
Projects hub form, and
-
Overall % Cmplt on the
Project Budget Worksheet form.
When you save a change to this value in any of these locations, the value automatically updates in all the corresponding locations.
|
Labor % Complete
|
This column contains the same data as the following fields:
-
Labor Pct Comp on the Accounting tab of the
Projects hub form, and
-
Lab % Cmplt on the
Labor Cost/Burden or
Labor Billing tab of the
Project Budget Worksheet form.
When you save a change to this value in any of these locations, the value automatically updates in all of the corresponding locations.
|
Expense % Complete
|
This column contains the same data as the following fields:
-
Expense Pct Comp on the Accounting tab of the
Projects hubr form, and
-
Exp % Complt on the Expense Costs or Expense Billing tab of the
Project Budget Worksheet form.
When you save a change to this value in any of these locations, the value automatically updates in all of the corresponding locations.
|
Compensation
|
This column contains the same data as the following fields:
-
Compensation on the Accounting tab of the
Projects hub form, and
-
Compensation on the Summary dialog boxes of the
Project Budget Worksheet form.
When you save a change to this value in any of these locations, the value automatically updates in all of the corresponding locations.
|
Consultant Fee
|
This column contains the same data as the following fields:
-
Consultant Fee on the Accounting tab of the
Projects hub form, and
-
Consultant Fee on the Summary dialog boxes of the
Project Budget Worksheet form.
When you save a change to this value in any of these locations, the value automatically updates in all of the corresponding locations.
|
Reimb Allowance
|
This column contains the same data as the following fields:
-
Reimb Allowance on the Accounting tab of the
Projects hub form, and
-
Reimb. allowances on the Summary dialog boxes of the
Project Budget Worksheet form.
When you save a change to this value in any of these locations, the value automatically updates in all of the corresponding locations.
|
Total
Compensation
|
This column displays the total
compensation, calculated as:
Compensation +
Consultant Fee + Reimbursable Allowance.
|
Labor Budget
|
This column contains the same data as the total
Amount on the
Labor Cost/Burden tab of the
Project Budget Worksheet form.
|
Expense Budget
|
This column contains the sum of all budgeted non-consultant expenses on the Expense Costs tab of the
Project Budget Worksheet form.
|
Consultant Budget
|
This column contains the sum of all budgeted
consultant expenses on the Expense Costs tab of the
Project Budget Worksheet form.
|
Labor To Date
|
This column contains the total
job-to-date spent amount from the
Labor Cost and Burden tab of the
Project Budget Worksheet form. This number reflects total
labor costs posted to the
project.
|
Expense To Date
|
This column contains the sum of non-consultant
job-to-date spent amounts on the Expense Costs tab of the
Project Budget Worksheet form. This number reflects total expense costs, other than
consultant fees, posted to the
project.
|
Consultant To Date
|
This column contains the sum of
consultant
job-to-date spent amounts on the Expense Costs tab of the
Project Budget Worksheet form. This number reflects total
consultant fee costs posted to the
project.
|
Total Spent
|
This column contains the total
job-to-date spent amount on the Expense Costs tab of the
Project Budget Worksheet form. This number is also the sum of the three preceding columns:
Labor To Date, Expense To Date, and
Consultant To Date.
|
Percent Used
|
This column displays the total
job-to-date spent amount divided by the total
compensation.
|