Use the General tab to select report options for the Fee Remaining report and to save sets of options for reuse. 
  
 
	 Contents
 
		 
		| Field | Description | 
|---|
 
		   
			 | Report Name | You can change the default report name. | 
 
		   
			 | Exclude Completed Projects/Phases/Tasks | Select this check box if you do not want completed projects, phases, or tasks included in the Fee Remaining report. A project with phases or tasks is completed only if all items at lower levels of the work breakdown structure (WBS) are completed. | 
 
		   
			 | Print Project/Phase/Task Info | By default, the report has four columns: 
				  Fee, 
				  Percent Complete, 
				  Previous Fee, and 
				  Fee Remaining. 
				 Select this check box to display the following additional information for each project, phase, and task: 
				  
				   
					 Principal 
				   
					 Client 
				   
					 Compensation 
				   
					 Project Manager 
				   
					 Revenue Type 
				   
					 Total Job-to-Date Billed 
				   
					 Supervisor 
				   
					 Fee Method 
				   
					 Fee Job-to-Date Billed 
				   
					 Fee Basis 
				   | 
 
		   
			 | Exclude Previously Billed | Select this check box if you do not want the report to include previously billed amounts or percentages for projects that have billing schedules. | 
 
		   
			 | Scheduled Billing Date Range | Use this option to specify a range of scheduled billing dates to include in the report. |