Use the Columns tab to select or clear columns, change column sequence, provide new column labels, set column widths, or select number and date formats.
Sequence of Columns
If you include period columns based on your selection in
View By on the General tab, that selection (for example,
Week Periods) must be the last selected column in the grid on the Columns tab. The only exception is if you also select the
Planned Hours After column. That column can follow the period columns.
How Reporting Period and View by Options can Affect the Number of Columns You Select
DPS uses the reporting period and your selection in
View By on the General tab to determine the number of period columns to display. If you specify too long a period, the number of period columns can exceed the maximum of 20 columns. If that occurs, either specify a shorter reporting period or select a larger interval in
View By.
Asterisks (*)
If the values shown in the plan rows do not add up to the total shown in the corresponding totals line,
DPS marks the total with an asterisk.
Start and End Dates
DPS does not determine dates and durations for elements at higher levels of the work breakdown structure (WBS) by adding up durations at lower levels. Instead,
DPS determines the dates of an element at a higher WBS level as follows:
- The start date of a higher level element is the earliest start date assigned to one of the lower level elements under it.
- The end date of a higher level element is the latest end date assigned to one of the lower level elements under it.
Full-Time Equivalent (FTE) Values
Whether or not full-time equivalent values are displayed on the report is determined by the
Full-Time Equivalent (FTE) Reporting Includes options on the Inclusions tab. If you include them, the report displays the full-time equivalent values after the total row for each
organization and after the
Employee Final Total row.
Note that when it calculates the values for
FTE Over/(Under) Capacity,
DPS uses the rounded values displayed on the report in
FTE Capacity and Demand.
FTE Values and the Resource Assignment Column
If you include full-time equivalent values for capacity and demand, select
Resource Assignment as the first column for the report.
DPS displays capacity values with shaded backgrounds to help you distinguish them from demand values.
If you do not select
Resource Assignment as the first column, this shading does not display correctly.
Decimal Digits
Decimal settings for columns are determined by the
Hour Decimal Digits and
Amount Decimal Digits options on the Plan Settings tab of the Resource Planning Settings form.
Billable and Unbillable Time
Billable time in
DPS Planning is characterized as time that is mapped to regular
projects, or not mapped to overhead or promotional
projects. Nonbillable time in
DPS Planning only includes plans that are linked to overhead or promotional
projects.
Contents
Field | Description |
Resource Assignment
|
By default, the report groups data by
organization, with the
organization's identifier at the start of the data and totals for the
organization at the end of its data.
For each
employee within the
organization, this column displays the work breakdown structure (WBS) elements (projects,
phases, and
tasks) to which the
employee is assigned.
|
Total Available Hours
|
This column displays the total number of
employee work hours possible for the reporting period you specify on the General tab.
DPS calculates the available hours as follows: Hours per day * Number of working days in the reporting period.
The hours per day are from the Personal tab of the
Employees hub.
DPS determines working days based on holiday and non-working days set up for the active company.
Full-Time Equivalents (FTEs)
If you include
FTE Capacity and Demand rows, the
Total Available Hours column displays capacity as the number of full-time equivalents for all active
employees in the
organization or, at the end of the
employee data, for all active
employees in the active company. These values are not restricted to the
employees included on the report.
If you do not include the
Total Available Hours column on the report, the report displays only FTE demand, and the
Hours for All Active
Employees row is not displayed.
|
Total Planned Hours
|
This column displays the total number of planned hours for the
employee or generic resource for the reporting period you specify on the General tab.
Whether or not soft booked hours are included depends on the
Use Soft and Hard Booking for
Employee's Planned Hours option on the Resource Settings form and on the options in the
Show on Plan Level Rows group box on the General tab in the Options dialog box for the report.
Full-Time Equivalents (FTEs)
If you include full-time equivalent rows,
DPS displays the following in this column for those rows:
-
FTE Capacity and Demand: In these rows, the column displays the result of the following calculation:
(Total planned hours / Total available hours) * Total full-time equivalents
The total full-time equivalents value is displayed in the
Total Available Hours column for the row.
-
FTE Over/(Under) Capacity: In these rows, the column displays the over-capacity or under-capacity full-time equivalent values. The report displays under-capacity values in parentheses.
DPS calculates those values for this column as follows:
(Total Planned Hours from the FTE Capacity and Demand row) – (Total Available Hours from the FTE Capacity and Demand row)
An asterisk beside a total indicates that values on the plan rows do not add up to the total shown.
|
Soft Booked Hours
|
This column displays the number of soft booked hours. Hard booked assignments are those when an
employee is scheduled and approved on a plan, while soft booked is when an
employee is tentatively scheduled on a plan but the assignment has not yet been approved.
This column is available only if
Use Soft and Hard Booking for
Employee's Planned Hours is selected on the Resource Settings form.
Full-Time Equivalents (FTEs)
If you include full-time equivalent rows,
DPS displays the following in this column for those rows:
-
FTE Capacity and Demand: In these rows, the column displays the result of the following calculation:
(Total soft booked hours / Total available hours) * Total full-time equivalents
The total full-time equivalents value is displayed in the
Total Available Hours column for the row.
-
FTE Over/(Under) Capacity: In these rows, the column displays the over-capacity or under-capacity full-time equivalent values. The report displays under-capacity values in parentheses.
DPS calculates those values for this column as follows:
(Soft Booked Hours from the FTE Capacity and Demand row) – (Total Available Hours from the FTE Capacity and Demand row)
An asterisk beside a total indicates that values on the plan rows do not add up to the total shown.
|
Scheduled %
|
This column displays the percentage of available time that is scheduled. It includes both billable and nonbillable planned hours for all plans.
DPS calculates this value as follows: (Total Planned Hours /
Total Available Hours) * 100.
DPS rounds the result to a whole number. For example, if
Total Planned Hours is
103 and
Total Available Hours is
112,
DPS calculates the scheduled ratio as follows: (103 / 112) * 100 = 92%
Colors
DPS uses colors for this column to indicate
employees whose scheduled ratios exceed or fall short of expectations:
- If you select
Apply
Employee Utilization/Schedule Color Styles on the General tab and you select
All Planned Hours in
Resource Name Rows Include on the Inclusions tab,
DPS applies colors to the contents of this column based on the availability determination options on the Resource Settings form: red for over-utilized or over-scheduled, yellow for under-utilized or under-scheduled, and gray for properly utilized or properly scheduled..
- If you select
Apply
Employee Utilization/Schedule Color Styles on the General tab and you select
Only Billable Planned Hours in
Resource Name Rows Include on the Inclusions tab, no color is used.
Full-Time Equivalents (FTEs)
If you include full-time equivalent rows,
DPS displays the following in this column for the
FTE Capacity and Demand rows: (Total planned hours / Total available hours) * 100.
|
Utilization Target
|
This column displays the percentage of an
employee's hours that is expected to be billable. This percentage is specified in
Utilization Target on the Accounting tab of the
Employees hub.
Full-Time Equivalents (FTEs)
To calculate the full-time equivalent row value for the
Utilization Target column,
DPS does the following:
- Multiplies
employee hours per day (from
Hours/Day on the Employment Details tab of the
Employees hub) by the
employee utilization ratio (from
Utilization Target on the Employment Details tab of the
Employees hub).
- Adds the results for each
employee group together.
- Divides the total by the value in the
Total Available Hours column in the full-time equivalent row.
-
Divides the result by the full-time equivalent definition for hours pr day (from the Inclusions tab for the report).
|
Utilization %
|
This column displays the utilization percentage for billable planned hours. This percentage only includes billable time on plans marked to include in utilization.
DPS calculates this value as follows: (Billable Planned Hours / Total Available Hours) * 100
Whether or not soft booked hours are treated as planned hours depends on the
Soft and Hard Booking options on the Resource Settings form.
Colors
DPS uses color in this column to indicate
employees whose billable utilization values exceed or fall short of expectations:
- If you select
Apply
Employee Utilization/Schedule Color Styles on the General tab and you select
Only Billable Planned Hours in
Resource Name Rows Include on the Inclusions tab,
DPS applies colors to the contents of this column based on the utilization determination options on the Resource Settings form: red for over-utilized or over-scheduled, yellow for under-utilized or under-scheduled, and gray for properly utilized or properly scheduled..
- If you select
Apply
Employee Utilization/Schedule Color Styles on the General tab and you select
All Planned Hours in
Resource Name Rows Include on the Inclusions tab, no color is used.
Full-Time Equivalents (FTEs)
If you include full-time equivalent values, this column displays the group's billable utilization percentage in the full-time equivalent row:
- For
organizations,
DPS totals the utilization percentages for all active
employees in the
organization and divides that total by the number of active
employees in the
organization.
- For the final
employee total,
DPS totals the utilization percentages for all active
employees in the active company and divides that total by the number of active
employees in the company.
|
Planned Hours Start Date
|
This column displays the date of the first day in the reporting period for which planned hours exist. (This date may or may not coincide with the starting date of the first interval.) For resource rows,
DPS includes only plans included in utilization.
|
Planned Hours End Date
|
This column displays the date of the last day in the reporting period for which planned hours exist. (This date may or may not coincide with the ending date of the last interval.) For resource rows,
DPS includes only plans included in utilization.
|
(View By) Periods
|
Select the
Periods option on the Columns tab to include the period columns defined by the
Reporting Period and
View By options on the General tab. (The actual column name that appears in the grid on the Columns tab depends on the
View By option you select. For example, if you select
Month, you select
Month Periods in the grid on the Columns tab to include the monthly period columns on the report.)
Your settings for the
View By and
Reporting Period options on the General tab determine the headings and contents of the period columns. For example, if you make the following entries, the report displays one column for each of the four months in the reporting period:
-
View By = Month
-
Reporting Period = 6/1/19 to 9/30/19
The heading for each column in this example consists of the month and date range:
Jun 19 1 - 30
An asterisk beside a total indicates that values on the plan rows do not add up to the total shown.
Date Format
If the headings for the period columns include full dates,
DPS always uses the Short Date format from your Regional Options in Microsoft Windows. Unlike most other dates, the format of these dates is not determined by the default date format for the report on the Layout tab of the Options dialog box.
Colors
If you select
Apply
Employee Utilization/Schedule Color Styles on the General tab and you select
Only Billable Planned Hours in
Resource Name Rows Include on the Inclusions tab,
DPS applies colors to the contents of this column based on the utilization determination options on the Resource Settings form.
If you select
Apply
Employee Utilization/Schedule Color Styles on the General tab and you select
All Planned Hours in
Resource Name Rows Include on the Inclusions tab,
DPS applies colors to the contents of this column based on the availability determination options on the Resource Settings form.
Totals in the Hours for Selected
Employees Row or Hours Row
If
employee rows contain hours, the
Hours for Selected
Employees row displays the sum of those hours. If
employee rows contain percentages,
DPS totals the percentages and divides the total by the number of
employees on the report. For generic resource rows,
DPS displays the sum of the hours from those rows. If the totals in the row include both
employee and generic resources, the value displayed is total hours for those resources, even if the
employee rows display percentages.
If
DPS displays an asterisk for one of the rows included in the total, it also displays an asterisk for the total.
Full-Time Equivalents (FTEs)
-
FTE Capacity and Demand row:
DPS calculates the period values for this row as follows:
(Sum of the hours for the
employee rows) / (Number of work days in the column period * Number of hours in one full-time equivalent)
If
employee rows contain percentages,
DPS uses the equivalent hours in this calculation.
-
FTE Over/(Under) Capacity row: In this row, the column displays the difference between the amount in the
Total Available Hours column in the full-time equivalent row and the amount in the current period column in that row.
|
Billable Goal Hours
|
This column displays the number of expected billable hours for the reporting period.
DPS calculates this as follows: Billable goal percentage * Total available work hours.
The billable goal percentage is based on the entry in
Utilization Ratio on the Accounting tab of the
Employees hub.
|
Billable Planned Hours
|
This column displays the billable planned hours for the reporting period.
Whether or not
DPS treats soft booked hours as planned hours depends on the
Soft and Hard Booking options on the Resource Settings form.
The options in the
Show on Plan Level Rows group box on the General tab determine whether or not
DPS includes hard booked and soft booked hours in plan rows.
Colors
DPS uses color in this column to indicate
employees whose billable planned hours exceed or fall short of expectations:
- If you select
Apply
Employee Utilization/Schedule Color Styles on the General tab and you select
Only Billable Planned Hours in
Resource Name Rows Include on the Inclusions tab,
DPS applies colors to the contents of this column based on the utilization determination options on the Resource Settings form.
- If you select
Apply
Employee Utilization/Schedule Color Styles on the General tab and you select
All Planned Hours in
Resource Name Rows Include on the Inclusions tab, no color is used.
An asterisk beside a total indicates that values on the plan rows do not add up to the total shown.
|
Planned Hours Before
|
This column displays the total planned hours for dates earlier than the start date of the reporting period. An asterisk beside a total indicates that values on the plan rows do not add up to the total shown.
|
Planned Hours After
|
This column displays the total planned hours for dates later than the end date of the reporting period. An asterisk beside a total indicates that values on the plan rows do not add up to the total shown.
|