The following is the list of fields that Deltek recommends you include in the import file. This is to ensure support for status entry in PM Compass, among other purposes.
For more information, see Schedule Import Overview.
Activity ID
MSP Unique ID (If you select the Use Microsoft Project Unique ID to Link Project Data option)
Description
Early Start
Early Finish
Late Start
Late Finish
Actual Start
Actual Finish
Baseline Start
Baseline Finish
Original Duration
Computed Remaining Duration
Physical % Complete
EVT (if available - user code/text field)
Activity ID
Resource ID
Budget
Remaining Quantity
Physical % Complete
Predecessor ID (or MSP Predecessors)
Successor ID
Relationship Type (part of MSP predecessors if importing from MSP)
Resource ID
Description
Unit
Resource Type
Learn about the Schedule Import form toolbar
Learn about the correct format for schedule import files
Modify a schedule import configuration