Your project job-to-date expense budget lets you keep track of all expenses to be charged to a project. Use this tab to establish your expense costs. If your system administrator enabled reporting at burdened rates, this is the Expense Burden tab. 
  
 
	 Contents
 
		 
		|  Field  |  Description  | 
 
		   
			 |  Start Date 
			  | 
 
			  Enter the start date for work on this account or click 
				  and select a date. 
			  | 
 
		  
 
		   
			 |  End Date 
			  | 
 
			  Enter end date for work on this account or click 
				  and select a date. 
			  | 
 
		  
 
		   
			 |  Overall % Cmplt 
			  | 
 
			  In this field, enter an overall percent complete for the entire project. If you do so, the percentage you specify here overrides the overall percent complete that Vision calculates. 
			  | 
 
		  
 
		   
			 |  Exp % Cmplt 
			  | 
 
			  For any project, you can define an overall expense percent complete, an overall labor percent complete, or both, for your project: 
				 
				  -  You define the overall expense percent complete here in the 
					 Exp % Complt field. 
				  
 
 
				  -  You define the overall labor percent complete in the 
					 Lab % Complt field on the Labor Billing tab or Labor Costs tab. 
				  
 
 
				 
 
			  | 
 
		  
 
		   
			 |  Project Currency 
			  | 
 
			  This field displays the three-digit code for the project currency of the project selected. 
			  | 
 
		  
 
		
 
	  
 
	 Expense Costs Grid
 
		 
		|  Field  |  Description  | 
 
		   
		    Insert 
		   | 
 
		  Click this option to insert a row beneath the current row. 
		   | 
 
		
 
		   
		    Delete 
		   | 
 
		  Click the row to select it, then click this option to delete the row. 
		   | 
 
		
 
		   
			 |  Account 
			  | 
 
			  Your expense budgets are based on account numbers. You can insert a new row to add a new budget line for any account number that is valid for the current project. 
				 When you insert a row, you can enter an account in this field or click 
				    and select an account from the lookup. 
				 
 
			  | 
 
		  
 
		   
			 |  Account Name 
			  | 
 
			  This field displays the name of the expense account. 
			  | 
 
		  
 
		   
			 |  Vendor 
			  | 
 
			  Enter the vendor number for which to enter a budget for this project or click 
				  to display the Vendor lookup and select one of the vendors listed. 
			  | 
 
		  
 
		   
			 |  Vendor Name 
			  | 
 
			  This field displays the name of the vendor. 
			  | 
 
		  
 
		   
			 |  Pct Complete 
			  | 
 
			  Enter your estimate of how far work has progressed on the project for this account. Deltek recommends that you update the percent complete on a regular basis. 
			  | 
 
		  
 
		   
			 |  Amount 
			  | 
 
			  Enter the budgeted monetary amount for the expense charged to the account for the project. 
			  | 
 
		  
 
		   
			 |  EAC Amt 
			  | 
 
			  Estimate at Completion Amount 
				 Enter your estimate of the total cost amount that will have been incurred at the completion of the project, as reported for this account. 
				 
 
			  | 
 
		  
 
		   
			 |  ETC Amt 
			  | 
 
			  Estimate to Complete Amount 
				 Enter your estimate of the total additional cost amount required to complete the work for this account. 
				 
 
			  | 
 
		  
 
		   
			 |  Start Date 
			  | 
 
			  Enter the start date for work on this account or click 
				  and select a date. 
			  | 
 
		  
 
		   
			 |  End Date 
			  | 
 
			  Enter the end date for work on this account or click 
				  and select a date. 
			  | 
 
		  
 
		   
			 |  JTD Spent 
			  | 
 
			  This field shows the actual cost amount spent, job-to-date, for this account, as calculated at the most recent posting. 
				 If you use the Multicurrency feature, this amount displays in the project currency of the selected project. 
				 
 
			  |