Use the Columns tab to select or clear columns, change column sequence, provide new column labels, set column widths, or select number and date formats. 
  
 
	 Contents
 
		 
		|  Field  |  Description  | 
 
		   
			 |  Task 
			  | 
 
			  This column displays the work breakdown structure (WBS) component. 
			  | 
 
		  
 
		   
			 |  Planned Hours 
			  | 
 
			  This column displays the total planned labor hours for the WBS component from the current plan. 
			  | 
 
		  
 
		   
			 |  JTD Hours 
			  | 
 
			  This column displays the actual job-to-date hours charged to the WBS component as of the date specified on the Date Basis tab. 
			  | 
 
		  
 
		   
			 |  ETC Hours 
			  | 
 
			  This column displays the estimate-to-completion hours for the WBS component. The estimate-to-completion hours are the estimated number of planned labor hours necessary to complete the work, starting from the date specified on the Date Basis tab. 
			  | 
 
		  
 
		   
			 |  Planned EAC Hours 
			  | 
 
			  This column displays the estimate-at-completion hours for the WBS component. The estimate-at-completion hours are the estimated total number of labor hours necessary to complete work. Vision calculates the planned estimate-at-completion hours as follows: 
				JTD Hours + ETC Hours 
			  | 
 
		  
 
		   
			 |  Planned – EAC 
			  | 
 
			  This column displays the variance between the total planned hours from the current plan and the estimate-at-completion hours: 
				Planned Hours – Planned EAC Hours
			  | 
 
		  
 
		   
			 |  % Complete (JTD/Planned) 
			  | 
 
			  This column displays the percent complete based on total planned hours from the current plan. Vision calculates the percent complete as follows: 
				JTD Hours / Planned Hour 
			  | 
 
		  
 
		   
			 |  % Complete (JTD/EAC) 
			  | 
 
			  This column displays the percent complete based on estimate-at-completion hours. Vision calculates the percent complete as follows: 
				JTD Hours / Planned EAC Hours 
			  |