| Microsoft Project Field | Vision Field |
|---|---|
| Project Name | Plan Name |
| Project Start Date | Start Date |
| Project Finish Date | End Date |
| SUM Baseline Labor | Baseline Labor Hours |
| SUM Planned Labor | Planned Labor Hours |
| SUM Baseline Cost | Baseline Labor Cost |
| SUM Planned Cost | Planned Labor Cost |
| Task Name | Task Name |
| Task Start | Start Date |
| Task Finish | End Date |
| Task Baseline Work | Task Baseline Labor Hours |
| Task Work | Task Planned Labor Hours |
| Task Baseline Cost | Task Baseline Labor Cost |
| Task Cost | Task Planned Labor Cost |
| Standard Rate | Assignment Cost Rate |
| Assignment Start | Assignment Start Date |
| Assignment Finish | Assignment End Date |
| Assignment Baseline Work | Assignment Baseline Labor Hours |
| Assignment Work | Assignment Planned Labor Hours |
| Assignment Baseline Cost | Assignment Baseline Labor Cost |
| Assignment Cost | Assignment Planned Labor Cost |
| Predecessor | Predecessors |
| Type | Relationship (Finish-to-Start, Start-to-Start, and so on) |
| Lag | Lag/Lead (positive or negative number of days) |
| Vision Field Defaults | |
| Percent Complete Formula defaults to "User-Entered Percent Complete" | |
| Available to Other Users defaults to " Y" | |
| Show Unposted Actual Labor defaults to " N" | |
| Include this Plan in Utilization calculation defaults to "N" | |
| RPPlan.GenResTableNo defaults to the first labor category billing rate table marked as available for Planning | |
| Cost Rate Method defaults to "0" | |
| Billing Rate Method defaults to "0" | |
| Cost Rate Table defaults to "0" | |
| Billing Rate Table No defaults to "0" |