Labor Multiplier Fields

The Labor Multipliers display on the top right of the Labor Planning page.

Contents

Field Description
Labor Target Multiplier This multiplier is used as the basis for evaluation against the Labor EAC multiplier. The multiplier represents how much revenue is anticipated for each labor cost dollar spent on a project. If you are viewing a Vision plan, this field displays the Target Multiplier for Cost on the General tab of Vision > Project Planning. If you are viewing a Navigator plan, this field displays the Target Multiplier that is assigned in Plan Settings. If the project has no plan, no multiplier displays.

Calculation: Target Labor Cost Multiplier for the plan

If a project is mapped to multiple Vision plans that have the Include in utilization and project reports option selected, Navigator shows the target multiplier for the plan with the earliest creation date.

Labor EAC Multiplier The estimate-at-completion (EAC) labor cost amount is the cost value of hours worked through today and the remaining planned hours.

Only the EAC cost amounts from plans in utilization are included in the calculation. All Navigator plans are marked to Include in utilization and project reports. Vision plans may or may not be marked as such.

Calculation: Labor EAC Multiplier = Contract / EAC cost

If your firm uses the Multicurrency feature in Vision, all amounts are in the project (cost) currency, and the currency in use is indicated next to the Billing and Cost options.