Detailed Timesheet Report
The Detailed Timesheet report displays timesheet entries by employee and labor period. The report includes all information entered on the employee's timesheet.
Contents
Timesheet Hours
Report Header: Timesheet Hours Tab
Column | Description |
---|---|
Employee |
The field displays the employee's identification number and name (Last Name, First Name). |
Signed/Approved |
If you are not using the electronic signature feature, these lines are blank. In either case, you can use the lines for handwritten signatures if you wish. The current status of the timesheet also displays in this section, as follows:
|
Organization |
Report Columns: Timesheet Hours Tab
Column | Description |
---|---|
Project |
These columns display the number and name of the project to which the employee is charging time. Items in these columns display on the report in the following order:
|
Phase |
These columns display the number and name of the phase for which time was entered, if applicable. |
Task |
These columns display the number and name of the task for which time was entered, if applicable. |
Labor Code |
The labor code number to which the employee is charging time is shown below the project number and name (or the phase/task number if applicable). |
Labor Category |
The labor category for which the employee is charging time is shown below the labor code number, if applicable. Labor category information displays on the report only if you are using Vision Accounting, Vision Billing, or Vision Resource Planning. |
Payroll Tax Locale |
The project's payroll tax locale (for example, CA, MA, or NY) is shown below the labor category information, if applicable. |
Client Name |
The name of the client associated with a project displays on the same row as the project name and number. |
Comments |
If the employee has entered any comments about time charged to a specific project, phase, and/or task, the comments display below the Day/Date boxes for the associated project, phase, and or task. The comment is preceded by a date to indicate the charge to which the comment applies. Comments display only if you selected Include comments on detailed timesheet report on the Setup tab of Company Timesheet Configuration. The expanded text content in this field displays on the report if you select Include Comments on the Setup tab in Company Timesheet Configuration. |
Total ( Reg., Ovt, Ovt-2) |
In this section, the Total column displays total regular and/or overtime hours charged to each individual project, phase, and/or task for the selected labor period.
The Ovt and Ovt-2 boxes display only if overtime hours are entered on the timesheet. |
Day/Date |
There is a separate column on the report for each day in the selected labor period. Each column shows the day of the week and the corresponding calendar date. Within each column, there is a Reg., Ovt, and Ovt-2 box for each project on the timesheet report. These boxes show the regular, overtime, and secondary overtime hours the employee has charged to each project, phase, and/or task for each day in the labor period. The Ovt and Ovt-2 boxes display only if overtime hours are entered on the timesheet. |
Daily Totals Section: Timesheet Hours Tab |
|
Daily Totals |
In this section, the Total column displays total regular and/or overtime hours charged to all projects, phases, and/or tasks for the selected labor period.
The Ovt and Ovt-2 boxes display only if overtime hours are entered on the timesheet. |
Unit Quantities
Report Header
Column | Description |
---|---|
Employee |
The employee's identification number and name (Last Name, First Name) display here. |
Signed/Approved |
If you are not using the electronic signature feature, these lines are blank. In either case, you can use the lines for handwritten signatures if you wish. The current status of the timesheet also displays in this section, as follows:
|
Organization |
Report Columns
Column | Description |
---|---|
Project |
This column displays the number of the project to which the employee is charging units. |
Phase |
This column displays the number of the phase for which unit quantities were entered, if applicable. |
Task |
This column displays the number of the task for which unit quantities were entered, if applicable. |
Unit |
The unit name to which the employee is charging units displays in this column. |
Unit Table |
The unit table to which the employee is charging units displays in this column, if applicable. |
Total |
In this section, the Total column displays total units charged to each individual project, phase, and/or task for the selected labor period. |
Day/Date |
There is a separate column on the report for each day in the selected labor period. Each column displays the day of the week and the corresponding calendar date. Within each column, there is a box for each project on the timesheet report. These boxes display the total units the employee has charged to each project, phase, and/or task for each day in the labor period. |
Daily Totals Section | |
Daily Totals |
In this section, the Total column displays total units charged to all projects, phases, and/or tasks for the selected labor period. |