Cobra Help

Add a New Work Package using the Dialog Box

Use the Add Work Package dialog box to add a new work package to the selected control account.

To add a new work package using the dialog box:

  1. Display the Project view and take one of the following actions:

    • In the Tasks group on the Edit tab, click Add Work Package.
    • Right-click the Spreadsheet pane and select Add Work Package (Ctrl+W) on the shortcut menu.
  2. Use the fields and options in the Add Work Package dialog box to create a new work package.

  3. Click OK to add the new work package to the selected control account.