Criteria Page of the Replan Wizard

Use this page to select which project code you want to replan.

Contents

FieldDescription
Criteria

Use this field to select one of the following options:

  • Total Project
  • Control Account
  • Work Package
  • Control Account Key Fields
  • Work Package Field
  • Control Account Codes 1 to 20
  • Work Package Codes 1 to 20
  • CAM
  • Work Package Manager
  • Progress Technique

If the code you selected has a hierarchical structure, the Replan process includes that code and its children if the Include all children option is selected.

Selection

This field is available only if you selected a criterion other than Total Project in the Criteria field.

Click to display the Code Lookup dialog box, where you can select the code that you want to include in the process. For example, if you selected Control Account in the Criteria field, the Code Lookup dialog box displays all control accounts for the selected project.

Include all children

This option is available if you select a code with children in the Selection field. Selecting this option instructs Cobra to run the process against the parent code and its children. For example, if you selected WBS code 1 in the Selection field and this has child codes 1.1 and 1.2, then Cobra will run the process against codes 1, 1.1, and 1.2.

This option is enabled only for code criteria that are hierarchical in nature, such as WBS and OBS.


How to...

Perform Project Replan

Calculate Progress

Select the Earned Value Method

Select the Level at Which to Capture Actual Costs


Learn more about...

Replan

Replan Preferences

Progress Techniques


Parent Topic: