Cobra Help

Spread Curve Dialog Box

Use this dialog box to spread budgets using the spread methods that have been previously defined on the Spread Curves tab of the Application Preferences dialog box.

Select the spread curve method that you want to use, and click Select. Cobra spreads the budget using the spread curve method that you selected and displays the updated information in the Time-phase pane or Time-phase Detail pane.

Note: For more information on the spread curves, see Spread Curves Tab of the Application Preferences Dialog Box.

Display the Spread Curve Dialog Box

Use this procedure to display the Spread Curve dialog box.


How to...

Display the Project View

Spread Budgets Using Pre-defined Spread Methods

Spread Updated Budgets for Resources

Adjust Budget Spreads Manually

Reconcile Budgets and Forecasts


Learn more about...

Spreadsheet Pane of the Project View

General Tab of the Project View

Milestones/Steps Tab of the Project View

Notes Tab of the Project View


Parent Topic:

Time-phase Detail Pane of the Project View