Change the Dates on a Resource Plan

By default, resource plans display dates starting from the current week. To view and modify resourcing for past dates, you can change the date range.

To change the dates on a resource plan:

  1. On the resource plan toolbar, click on the From and To fields and select the start and end dates.
  2. Click Search to update the resource plan.