Expenses Plan Settings

Use the Expenses options on the Plan Settings dialog box to specify the planning level, rates, and multipliers for planned expenses on your plans.

This dialog box automatically displays when you create a new Navigator plan or you convert a Vision plan to a Navigator plan.

You can establish the Expenses Plan Settings under the following conditions:

Location

To display the Expenses page of the Plan Settings dialog box, complete the following steps:
  1. Select a project that has a Navigator plan.
  2. Click and select Plan Settings. The Plan Settings option does not display if the project does not have a plan, the plan is a Vision plan, or if you do not have appropriate access rights.
  3. Navigator automatically checks out the plan when the Plan Settings option is selected, you have appropriate access rights, and no one else has the plan checked out.
  4. Select the Expenses option. The Expenses Plan Settings fields display.

Contents

Field Description
Planning Level
Use this drop-down list to select the default WBS level that will be used to plan expenses for the project:
  • Project: Select this option to plan expenses at the Project level.
  • Phase: Select this option to plan expenses at the Phase level, if the project has phases. Otherwise, expenses are planned at the Project level.
  • Lowest Level: Select this option to plan expenses at the lowest level of the WBS.

The options in this list are based on the WBS settings that are defined in Vision > Utilities > Key Formats. For example, if the Phase length is set to zero, then Project is the only option that displays in the Planning Level list.

Note: You cannot change the planning level if the project has a baseline plan and planned expense amounts, or if your security access does not allow you to change the baseline.

Changing the planning level has multiple implications if the existing plan includes resource rows that are planned under a level that is different than the new level:

  • Any planned resource rows under a WBS level that does not match the new planning level are removed.
  • If any of the planned resource rows to be removed are included in the baseline and you have access rights to change the baseline, the rows will be removed from the baseline. Note that removing rows from the baseline may impact the ETC. If your access rights don't allow you to change the baseline, you cannot change the planning level.
  • Any planned resource rows already at the new planning level remain.
  • Resource rows with JTD will be shown at the new planning level once the change is finished.
  • If the plan is not balanced (where some phases have tasks and some do not) and you select Lowest Level, Navigator will remove the resource rows that are lower than the selected level.
  • Changing the level to a lower one and the project has the lower level and there are resource rows under a higher level. All the resource rows are removed.
Reimb. Expense Billing Markup Use these fields to define the settings for reimbursable expense planned amounts on Regular projects.
Note: If the Budget Type is set to Cost, or the Use Billing Currency not Project Currency option is selected on the Rates tab of Vision > Accounting > Configuration and the project currency is not equal to the billing currency, the Rate Method automatically defaults to None and the Rate Method, Rate Table, Recalculate, and Multiplier fields are display-only.
Recalculate Select this option to apply the current settings and recalculate the planned bill amounts for reimbursable expenses. You must click Save for the recalculation to occur.
Rate Method Select one of the following Rate Method options:
  • Multiplier Only: The planned billing amount will be calculated as Planned Cost x Multiplier.
  • From Account Rate Table: The planned billing amount will be calculated using the rate for the expense account from the specified table. If no rate is found, Planned Cost x Multiplier will be used.
  • From Category Rate Table: The planned billing amount will be calculated using the rate for the expense category from the specified table. If no rate is found, Planned Cost x Multiplier is used.
  • None: The planned billing amount will be set equal to the planned cost.

The Rate Method is initially set to the default value that is defined in Vision > Configuration > Planning > Plan Settings.

If Rate Method is set to None, only billing amounts are visible. If the Rate Method is set to Multiplier Only, From Account Rate Table, or From Category Rate Table, a Planned Cost or Planned Billing column displays on the Expenses grid. Use this field to view the planned cost or expense amounts at billing.

Rate Table

This option is available if you specify From Account Rate Table or From Category Rate Table as the Rate Method.

Use this field to specify the rate table that you want to use. This list contains either Expense Account Tables or Expense Category Tables, depending on the selected Rate Method. Only the tables you have access to display in the list, and they must also be marked as Available for planning in the Vision Billing application.

Multiplier Enter a multiplier to apply to all reimbursable expense entries when the Rate Method is set to Multiplier Only. If the Rate Method is set to From Account Rate Table or From Category Rate Table, the multiplier is applied to any account that is not found in the selected table.
Direct Expenses - Multiplier The multiplier is displayed for informational purposes only on Regular projects. The value is always 1.000 and cannot be changed. The planned cost and planned bill amounts for direct expenses are always equal to one another.
Indirect Expenses - Multiplier The multiplier is displayed for informational purposes only on Overhead and Promotional projects. The value is always 1.000 and cannot be changed.