Initial Settings for Expenses
When you create a new plan or convert an existing Vision plan, Vision Navigator uses expense data as the basis for the initial plan data. Many of these values are set internally for the plan and are not visible in Navigator.
Vision Settings | Impact in Navigator |
---|---|
The following settings depend on the use of the Vision Planning module. If in use, they display on the General tab in | . If not in use, they display on the main form in .|
Enable Expense Planning | Select this option to plan expenses in Navigator. |
Show Committed PO Expenses. | This option is automatically selected and is used internally in Navigator. |
Calculate Expense Billing from Cost. | This option is used internally in Navigator. |
General Conversion Settings | |
Baseline amount | Converted at same level as planned |
Baseline time-phased assignments. | Remain in original time-phase assignment. Time-phased expense assignments are not visible in Navigator. |
Expenses are planned at project level. | Expenses Planning Level automatically set to Project. |
Expenses are planned at the lowest level of the WBS. | Expenses Planning Level automatically set to Lowest Level. |