When you create a new plan, Vision Navigator uses project data as the basis for the initial plan data. Many of these values are set internally for the plan, but are not visible in Navigator. You can review the settings in Vision Project Planning.
Plan Value | Default Setting |
---|---|
Plan Name | Project Name |
Plan Number* | Project Number |
Start and End Dates | Project's Initial Dates: Start and Completion Dates: Estimated dates. If only one date exists, it is assigned as both the start and end dates. If neither date exists, tomorrow's date is assigned for both dates. These dates expand and contract to allow for the earliest and latest lower level start and end dates on lower level WBS rows. |
Calendar Scale | Defined in Vision's Plan Settings. If your firm uses Vision Multicompany feature, the default scale is defined in the project company's Plan Settings. |
Starting Day of Week* | Monday |
Budget Type | The budget type defaults from Vision's Plan Settings. If you are also using Vision Multicompany, the budget type instead defaults from Vision's Plan Settings that are established for the project's company.
If the Allow Changes to Budget Type option is selected on the Navigator tab in Configuration > Roles > Security, you can use Navigator's Plan Settings to change the budget type for each individual plan. |
Include in Utilization and Project Reports* | This option is selected. |
% Complete Formula* | JTD/(JTD+ETC) |
Show Unposted Actual Labor* | This option is selected. |
Show Committed PO Expenses* | This option is selected. |
Available to Other Users* | This option is selected. |
Status* | Active |
Planned Revenue: Labor Multiplier Type* | Depends on the Budget Type setting:
|
Planned Revenue: Reimbursable Method* | Depends on the Budget Type setting:
|
ETC/JTD Date Basis | Today's Date |
Opportunity | Project's Opportunity |
Primary Client | Project's Primary Client |
Principal | Project's Principal |
Supervisor | Project's Supervisor |
Project Manager | Project's Project Manager |
Probability from Opportunity, if project is linked to an opportunity | Probability on Project's Opportunity |
* Not visible in Vision Navigator. |
- Initial Settings for Consultants
When you create a new plan or convert an existing Vision plan, Vision Navigator uses consultant data as the basis for the initial plan data. Many of these values are set internally for the plan and are not visible in Navigator. - Initial Settings for Expenses
When you create a new plan or convert an existing Vision plan, Vision Navigator uses expense data as the basis for the initial plan data. Many of these values are set internally for the plan and are not visible in Navigator.
Parent Topic: Project Management Configuration