Set WIP Values of Jobs of Monthly WIP Adjustments to Zero

Use the Monthly WIP Adjustments Follow-up submodule to set the WIP values of the jobs of monthly WIP adjustments to zero.

To use the Monthly WIP Adjustments Follow-up submodule, you must have access to Tasks as defined in the User Access Rights submodule under Settings.

To set the WIP value of the job of a monthly WIP adjustment to zero:

  1. On the main toolbar, click Tasks .
  2. In the left pane of the Tasks screen, click Follow-up > Monthly WIP Adjustments Follow-up.
  3. Highlight the job of the monthly WIP adjustment whose WIP value you want to set to zero.
  4. On the grid toolbar, click and select Set WIP value to zero for selected jobs.
  5. In the Make Adjustment for Selected Jobs dialog box, make any necessary adjustments to the date and approval status.
  6. Click OK.