System Variable 754: Do Not Run Approval Work Flows on Imported Calendar Appointments (Task)

Use this System Variable to determine if normal approval flows for task resource bookings should apply to the tasks that were imported into WorkBook via calendar synchronization.

When this System Variable is enabled, WorkBook does not apply the approval flow set in Settings > Company Approvals > Task Resource Booking Approval to the tasks that were imported via calendar synchronization.
Note: Imported calendar appointments usually do not need approvals.

This System Variable is enabled by default.

It may be necessary to perform a refresh when modifying System Variable values.