Rank Sprint Items on the Scrum Board

Use the Scrum Board submodule to rank sprint items.

To use the Scrum Board submodule, you must have access to Scheduling as defined in the User Access Rights submodule under Settings.

To rank sprint items on the Scrum board:

  1. On the main toolbar, click Scheduling .
  2. On the side toolbar of the Scheduling screen, click Schedule Overview > Scrum Board.
  3. Click the Scrum Board tab.
  4. On the tab toolbar, select a sprint from the drop-down menu.
  5. Drag and drop an item to a new position within the same column or to another column.
  6. To rank multiple items all at once:
    1. Press and hold CTRL.
    2. Select the items that you want.
    3. Drag and drop your selection to a new position within the same column or to another column.
    Tip: The total number of tasks for each column is displayed to the right of the column header.